Project
Descriptions
|
|
Village of Hobart
Water
Supply and Treatment
System
Project
|
|

Water Treatment Plant, Hobart, New
York
|
|
This project entails developing a new groundwater
source to replace an existing well under Order on Consent from NYSDEC, and
upgrading the water treatment facility and tank transmission main for this
community with a design average water consumption of 75,000 gpd. This project is currently in the design phase.
Engineering
and Planning services are being provided for all phases of the project as
follows:
|
|
|
-
Preliminary
Engineer’s Report
-
Facility Plan of Proposed Facilities
-
Funding
Application Assistance
-
Water Supply
Application
-
Test
Production Well Development
-
Well Siting and Test Drilling
-
Final Design and Specifications
-
Bidding Assistance
-
Construction
Administration
-
Full-time Construction
Observation
|
|
The major components of the project included the
following:
|
|
|
-
New Production Wells
-
New Well Control Building
-
New 3,000 L.F. raw water transmission main
-
Water Treatment Plant for radon, iron and manganese
removal, including treatment process equipment, motor control center, master
control panel for system controls, high lift pumps, chemical feed system, and
process piping
-
New 2,100
L.F. Tank Transmission Main
|
|
|
|