This
project for supply, treatment, and distribution improvements for a community
with an average water consumption of 100,000 gpd is currently in the design
phase. The following Engineering
services are being provided:
|
|
|
-
Preliminary Engineer’s Report
-
Water Supply Application
-
Funding
Application Assistance
-
Facility
Plan of Proposed Facilities
-
Well Siting
-
Final Design and Specifications
-
Bidding Assistance
-
Construction Administration
-
Full-time Construction Observation
|
|
The
major components of the project are expected to include the following:
|
|
|
-
New Auxiliary
Well(s)
-
New Well Control Building
-
Water Treatment Plant Improvements,
including
replacement of motor control center, master control panel for system controls,
high lift pumps, chemical feed system, and modification of process piping
-
Distribution System Improvements, including water
main replacements, water main looping, valve replacements, and hydrant
replacements
-
Distribution Storage Repainting and Miscellaneous
Improvements
|
|

|
|